The Diary of an Extension
February... part one
2nd - Door frames inserted and room plastered |
9th - Scaffolding has been removed as the roof is complete |
![]() |
![]() |
9th - A start is made on the roof for the utility area | 9th - Mark and Pete continue to work on the roof |
![]() |
![]() |
12th - Upstairs windows are glazed | 13th - Wiring the kitchen |
![]() |
![]() |
13th - Laying the under-floor heating | 14th - Every Norman castle should have arrow slits... |
![]() |
![]() |