The Diary of an Extension

September 

  To Home Page

1st - Concreted foundations 4th - Signs of vertical movement -  a start is made on the blockwork
7th - The rainwater drain is laid 10th - Backfilling the gaps
24th - Holes are cut in the wall to take the beams for the floor 25th - The first beams are laid
27th - The remaining beams are in position 29th - Blocks fill in the gaps to make the floor